# Schedules | DRE

> Name schedules in schedules.yml, share timings, see when they fire, and run them from your orchestrator.

You're reading the docs for DRE 0.2 (v0.2.2). 0.3 adds messages, several outputs per report and when:, and changes nothing you wrote. [This page for 0.5](https://getdre.com/docs/schedules/) · [New in 0.5](https://getdre.com/docs/new-in-0.5/)

# Schedules

DRE doesn’t fire schedules itself; your orchestrator does. `schedules.yml` names them, and one report can have several, each with its own vars:

```yaml
- name: flash_daily
  report: sales_summary
  set: client_a
  cron: "0 7 * * *"
  timezone: Australia/Sydney
  vars: {period: day}
- name: close_monthly
  report: sales_summary
  set: client_a
  cron: "0 6 1 * *"
  timezone: Australia/Sydney
  vars: {period: month}
```

```bash
DRE_RUN_AT=2026-08-31T20:00:00Z dre run --schedule close_monthly
```

`--schedule` runs exactly the Bindings that schedule targets. Its `vars` sit above the report’s and below `--var`, and `run.schedule` renders as its name, so SQL can say `{% if var('period') == 'day' %}...`. Pass the instant the run was scheduled for through `DRE_RUN_AT` (or just the date through `DRE_RUN_DATE`) so reruns render the same: `DRE_RUN_AT` pins `run.now` and `run.scheduled_at` too, so a rerun of the 18:00 firing at 21:00 still renders as 18:00. `run_results.json`, the JSON events and `logs/dre.log` record the schedule, its vars, the scheduled instant (`scheduled_at`), every var the run used and the command’s parameters.

## See when schedules fire

`dre schedule ls` works out every firing in a window, so you can check a timing means what you think, and hand the list to an orchestrator:

```bash
dre schedule ls                                # the next 5 firings of each schedule
dre schedule ls -s sales_summary --limit 10    # when does this report run?
dre schedule ls --output json                  # every firing in the next 35 days, with its command
```

```text
TIME                   SCHEDULE       REPORTS
2026-09-01 06:00 AEST  close_monthly  sales_summary/client_a
2026-09-01 07:00 AEST  flash_daily    sales_summary/client_a
```

Each JSON occurrence carries the exact command that runs it (`argv` and `env`, with `DRE_RUN_AT` and `DRE_RUN_DATE` set), stable keys and hashes for change detection. See [Schedule occurrences](https://getdre.com/docs/v0.2/schedule-ls/) for the format, and the [orchestration recipe](https://getdre.com/docs/v0.2/orchestration/) for loading it into a scheduler.

## Share a timing

When many schedules fire at the same time (“the 1st of the month, 06:00 Sydney”), name the timing once in `timings.yml` and refer to it with `timing:`. Each schedule keeps its own report, Set and vars:

timings.yml

```yaml
month_start:
  cron: "0 6 1 * *"
  timezone: Australia/Sydney
  except: ["2027-01-01"]
```

schedules.yml

```yaml
- {name: close_client_a, report: sales_summary, set: client_a, timing: month_start, vars: {period: month}}
- {name: close_client_b, report: sales_summary, set: client_b, timing: month_start, vars: {period: month}}
```

A schedule has exactly one of `timing`, `cron`, `rrule` or `every`. With `timing`, it can’t set any of the timing’s own keys (`timezone`, `starting`, `at`, `except`, `also`): change the timing, or give the schedule its own. Timings and schedules are separate namespaces, and timing names follow the schedule-name rule. An unknown timing is an error and an unused one a warning. The [timings.yml reference](https://getdre.com/docs/v0.2/reference-timings/) lists every key.

## Skip dates, add dates, pause

```yaml
- name: weekday_flash
  report: sales_summary
  cron: "0 7 * * MON-FRI"
  timezone: Australia/Sydney
  except: ["2026-12-25", "2026-12-28"]   # holidays
  also: ["2027-01-02"]                   # a one-off Saturday run
- name: legacy_feed
  report: legacy_feed
  cron: "0 5 * * *"
  enabled: false                         # paused
```

-   `except` drops firings on those dates (in the schedule’s timezone). A date it doesn’t fire on changes nothing.
-   `also` adds firings on those dates, at the schedule’s time of day. It needs a timing that fires at one time of day: a cron with one minute and hour, `at`, or a rule with one `BYHOUR`. A date it already fires on is still one firing, and a date in both lists fires.
-   `enabled: false` pauses a schedule without deleting it. It keeps its name and settings, `dre schedule ls` lists it as paused with no occurrences, and `dre run --schedule` still runs it by hand.

## Run one report or Set of a schedule

A schedule that runs several Bindings can run just one of them, keeping the schedule’s vars and timezone:

```bash
dre run --schedule close_monthly -s sales_summary --set client_b
```

Selecting something the schedule doesn’t run is an error that lists what it does run. This is the command `dre schedule ls --split` puts in each occurrence, so an orchestrator can run, retry and track each report and Set on its own.

## What’s supported

### Timezone and DST

A schedule fires in, nearest first:

1.  its `timezone:` (or its timing’s),
2.  the project’s `timezone:` in `dre_project.yml`,
3.  UTC.

A report’s own timezone and `--timezone`/`DRE_TIMEZONE` never move a firing. When the run starts, the [run’s timezone](https://getdre.com/docs/v0.2/templates/#timezone) follows its usual order, where the schedule’s (or its timing’s) `timezone:` sits above the report’s. So a schedule without a `timezone:` fires in the project’s timezone but runs in the report’s: `dre validate` warns when they differ. Setting `timezone:` on the schedule or timing keeps them together.

-   A time that doesn’t exist (the clocks go forward over it) fires at the first instant after the gap: 02:30 on the day Sydney moves from 02:00 to 03:00 fires at 03:00.
-   A time that happens twice (the clocks go back) fires once, the first time.
-   Firings that land on the same instant are one firing.
-   The run date is the firing’s date in its timezone: 06:00 on the 1st in Sydney is the run for the 1st, though it’s still the 31st in UTC.

### cron

Five fields, `minute hour day-of-month month day-of-week`:

Field

Values

Names

minute

0-59

hour

0-23

day-of-month

1-31

month

1-12

`jan`\-`dec`

day-of-week

0-7 (0 and 7 are Sunday)

`sun`\-`sat`

Each field takes `*`, a value, a list (`1,15`), a range (`1-5`, `mon-fri`) and a step (`*/15`, `0-30/10`). Names are case-insensitive. The macros `@yearly` (`@annually`), `@monthly`, `@weekly`, `@daily` (`@midnight`) and `@hourly` stand for their usual expressions.

**Both day fields.** When either day field starts with `*`, a day must match both (one of them being every day, or a step over every day): `0 6 */2 * MON` is odd-numbered days that are Mondays. When both are restricted, a day matching either is enough: `0 6 1,15 * MON` is the 1st, the 15th and every Monday. This is classic cron’s rule.

Not supported: seconds and year fields, and the `L`, `W`, `#` and `?` extensions. Use an `rrule` for “the last weekday” or “the 2nd Tuesday”.

### rrule

An [iCalendar recurrence rule](https://datatracker.ietf.org/doc/html/rfc5545#section-3.3.10) (the `RRULE:` prefix is optional):

Part

`FREQ`

`HOURLY`, `DAILY`, `WEEKLY`, `MONTHLY` or `YEARLY` (required).

`INTERVAL`

Every N periods: `FREQ=WEEKLY;INTERVAL=2` is every other week. Needs `starting`.

`COUNT`

Stop after N firings, counted from `starting` (which it needs).

`UNTIL`

Stop after this date (`20261231`) or date-time (`20261231T180000`), read in the schedule’s timezone. Not with `COUNT`.

`BYMONTH`

1-12.

`BYMONTHDAY`

1-31, or -1 for the last day, -2 for the one before, …

`BYYEARDAY`

1-366 or negative.

`BYWEEKNO`

ISO week 1-53 or negative, with `FREQ=YEARLY`.

`BYDAY`

`MO`\-`SU`, optionally numbered in the month or year: `2TU` (2nd Tuesday), `-1FR` (last Friday).

`BYHOUR`, `BYMINUTE`

0-23 and 0-59: the time of day, instead of `at`.

`BYSETPOS`

Pick from each period’s set: `BYDAY=MO,TU,WE,TH,FR;BYSETPOS=-1` is the last weekday.

`WKST`

The first day of the week, for `INTERVAL` with weeks (default `MO`).

Rejected: `FREQ=SECONDLY`, `FREQ=MINUTELY` and `BYSECOND`; a minute is the finest grain. They’re errors (warnings on 0.1.x). A part that doesn’t fit its frequency, such as `BYMONTHDAY` with `FREQ=WEEKLY`, shows up as a problem in `dre schedule ls`.

### every

`every: {days: N}`, `{weeks: N}` or `{months: N}` counts from `starting`, at `at`. A start on the 29th-31st skips months without that day; for month ends, use `rrule: "FREQ=MONTHLY;BYMONTHDAY=-1"`.

### Anchors: `starting` and `at`

-   `starting` (`YYYY-MM-DD`) is the first date for `every` and rules. `every` needs it, and so does a rule with `INTERVAL` above 1, a `COUNT`, or one that takes its day from the start (a `WEEKLY`, `MONTHLY` or `YEARLY` rule without `BYDAY`, `BYMONTHDAY`, `BYYEARDAY` or `BYWEEKNO`). Without it the firings would depend on when you look.
-   `at` (`HH:MM`) is the time of day, unless the rule sets `BYHOUR` or `BYMINUTE` itself.
-   With no time given, a schedule fires at 00:00 in its timezone, and `dre validate` warns.
-   Cron schedules take neither: the expression sets the days and the time.

A missing `starting` is an error (a warning on 0.1.x).

### Worked examples

Firings from 3 October 2026, in Sydney:

Timing

YAML

Fires

Every 2nd Tuesday at 07:00

`rrule: "FREQ=MONTHLY;BYDAY=2TU"`, `at: "07:00"`

13 Oct, 10 Nov, 8 Dec

The first weekday of the year

`rrule: "FREQ=YEARLY;BYDAY=MO,TU,WE,TH,FR;BYSETPOS=1"`, `at: "08:00"`

Fri 1 Jan 2027

The first Friday of March

`rrule: "FREQ=YEARLY;BYMONTH=3;BYDAY=1FR"`, `at: "09:00"`

5 Mar 2027

The first Friday of every month

`rrule: "FREQ=MONTHLY;BYDAY=1FR"`, `at: "09:00"`

6 Nov, 4 Dec, 1 Jan

Every 5 days from 2 October

`every: {days: 5}`, `starting: "2026-10-02"`, `at: "06:00"`

7 Oct, 12 Oct, 17 Oct

The last weekday of the month

`rrule: "FREQ=MONTHLY;BYDAY=MO,TU,WE,TH,FR;BYSETPOS=-1"`, `at: "18:00"`

30 Oct, 30 Nov, 31 Dec

29 February

`rrule: "FREQ=YEARLY;BYMONTH=2;BYMONTHDAY=29"`, `at: "06:00"`

29 Feb 2028

Every other Monday

`rrule: "FREQ=WEEKLY;INTERVAL=2;BYDAY=MO"`, `starting: "2026-10-05"`, `at: "09:00"`

5 Oct, 19 Oct, 2 Nov

Three runs, then stop

`rrule: "FREQ=DAILY;COUNT=3"`, `starting: "2026-10-05"`, `at: "10:00"`

5, 6 and 7 Oct

Fridays until the end of October

`rrule: "FREQ=WEEKLY;BYDAY=FR;UNTIL=20261031"`, `starting: "2026-10-01"`, `at: "16:00"`

9, 16, 23 and 30 Oct

Weekdays at 07:00

`cron: "0 7 * * MON-FRI"`

every weekday

06:00 on the 1st and 15th

`cron: "0 6 1,15 * *"`

15 Oct, 1 Nov, 15 Nov

Check any timing with `dre schedule ls --schedule <name>` before relying on it.